For a 1,500 sq ft ground floor, NextAwas takes about 4 to 5 months from the first day on site to handover. Around 2.5 months go into the structure and 2 to 2.5 months into finishing. Here is what happens in each stage, and what can stretch it.
Before work starts
Drawings, specifications and the bill of quantities are finalised before anyone digs. This step does not appear in the 4 to 5 months, but it decides whether they hold. A plan that changes on site is the most common reason a timeline slips.
Structure: about 2.5 months
Foundation, columns, slabs, brickwork and plaster. Under the BRIX-108 standard, each stage moves on only after its checks are signed off: steel and shuttering before every pour, materials when they reach the site. A check before the pour costs far less time than breaking and redoing work after it.
Finishing: 2 to 2.5 months
Flooring, doors, windows, electrical, plumbing and paint. The range depends on the package: a Premium or Luxury home has more ceilings, glass and fittings to install than an Essential one.
Handover
A final walkthrough against all 108 checkpoints. Then you get the keys.
What adds time
- More floors or a larger area. Each extra floor adds its own structure and finishing time.
- Design changes after work starts. A moved wall can mean broken plaster and new piping.
- Approvals. Delays in building approvals or connections hold the start or the handover.
- Weather. Heavy monsoon weeks slow slab and plaster work.
How to keep your home on time
Freeze the drawings before work starts, pick your fittings early, and choose a builder who puts a site engineer on your plot every day. At NextAwas you can follow every stage, check and site photo in your client portal, so you know whether the plan is holding without visiting the site.